At Stage 2 of the decision tree it shows that if a project is successful, the payoff will be $53,000 with a 2/3 chance of occurrence. There is also...
At Stage 2 of the decision tree it shows that if a project is successful, the payoff will be $53,000 with
a 2/3 chance of occurrence. There is also the 1/3 chance of a $24,000 payoff. The cost of getting to
Stage 2 (1 year out) is $24,000. The cost of capital is 15 percent. What is the NPV of the project at
Stage 1?
A. $349.16
B. $231.88
C. $108.17
D. $133.33
E. $147.59