BCF106 Fundam entals of Cost Analysis RESOURCES lesson 9 Time Phasing I PRINT I lesson 9 Overview Welcome to Time Phasing. Upon successful completion...

Subject: Time Phasing

If we were purchasing 24 tanks for operational use, funding the complete 24 chassis of the cost of the tanks in one year`s appropriation and funding the complete 24 turrets of the cost in the next year`s appropriation would be an example of:    

   A violation of annual funding

   The correct use of full funding

   A violation of full funding

   The correct use of annual funding