BUS 375 Greendale Project ReDux
When will the project be completed?
What is the critical path for the project?
How much slack / float are in your project? What activities have the greatest slack / float?
ID
Duration
Activity
Start
Free Slack
Total Slack
ID
Duration
Activity
Start
Free Slack
Total Slack
1
695 days
Baseball Stadium
2
70 days
Clear stadium site
0 days
0 days
3
30 days
Demolish building
0 days
0 days
4
70 days
Set up construction site
0 days
0 days
5
120 days
Drive support piling
0 days
0 days
6
120 days
Pour lower concrete bowl
0 days
0 days
7
120 days
Pour the main concourse
0 days
0 days
8
90 days
Install playing field
275 days
275 days
9
120 days
Construct upper steel bowl
0 days
0 days
10
140 days
Install seats
0 days
0 days
11
90 days
Build luxury boxes
155 days
155 days
12
30 days
Install Jumbotron
0 days
0 days
13
120 days
Stadium infrastructure
125 days
125 days
14
75 days
Construct steel canopy
0 days
0 days
15
30 days
Light installation
0 days
0 days
16
90 days
Build roof supports
5 days
5 days
17
180 days
Construct roof
5 days
5 days
18
90 days
Install roof tracks
95 days
95 days
19
90 days
Install Roof
5 days
5 days
20
20 days
Inspection
0 days
- @