BUS 375 Greendale Project ReDux

When will the project be completed?

What is the critical path for the project?

How much slack / float are in your project? What activities have the greatest slack / float?

ID

Duration

Activity

Start

Free Slack

Total Slack

ID

Duration

Activity

Start

Free Slack

Total Slack

1

695 days

Baseball Stadium

2

70 days

Clear stadium site

0 days

0 days

3

30 days

Demolish building

0 days

0 days

4

70 days

Set up construction site

0 days

0 days

5

120 days

Drive support piling

0 days

0 days

6

120 days

Pour lower concrete bowl

0 days

0 days

7

120 days

Pour the main concourse

0 days

0 days

8

90 days

Install playing field

275 days

275 days

9

120 days

Construct upper steel bowl

0 days

0 days

10

140 days

Install seats

0 days

0 days

11

90 days

Build luxury boxes

155 days

155 days

12

30 days

Install Jumbotron

0 days

0 days

13

120 days

Stadium infrastructure

125 days

125 days

14

75 days

Construct steel canopy

0 days

0 days

15

30 days

Light installation

0 days

0 days

16

90 days

Build roof supports

5 days

5 days

17

180 days

Construct roof

5 days

5 days

18

90 days

Install roof tracks

95 days

95 days

19

90 days

Install Roof

5 days

5 days

20

20 days

Inspection

0 days

Show more
Stephen Kogo
Stephen Kogo
  • @
  • 5 orders completed
ANSWER

Tutor has posted answer for $40.00. See answer's preview

$40.00

**** **** *** ******* be ***************** Completion Date: **** ******* ******** ** the ******** **** *** the **************** path *** ** ***** ******* **** slack * ***** *** in your ******** **** ********** have the ******** ***** * float? IDDurationActivityStartFree SlackTotal *******

Click here to download attached files: 9038879.docx
or Buy custom answer
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question