Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Can someone please show me how complete the following question?

Can someone please show me how complete the following question?

Question:Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for i = 1,...,5.

Write the appropriate constraint(s) for each condition. Conditions are independent.

a.   Choose no fewer than four projects.   

b.   If project 1 is chosen, project 5 must be chosen.   

c.   If project 2 is chosen, project 4 must not be chosen.   

d.   Projects cost 100, 200, 150, 75, and 300 respectively. The budget is 425.   

e.   No more than two of projects 2, 3, and 4 can be chosen.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question