Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is planning to install a pull system.

Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is planning to install a pull system. The process is being planned to have a usage rate of fifty pieces per hour. Each container is designed to hold ten pieces. It takes an average of thirty minutes to complete a cycle.(a) How many containers will be needed?