Answered You can hire a professional tutor to get the answer.
Chicago contractors got$5,400,000 contract to construct a school building for the City of Chicago.
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work on this contract began in 2013 and the financial data pertaining to this contract is available here.
Cost incurred till Dec.31, 2013 $1,080,000
Billings made to City $1,000,000
Amount collected from City $ 750,000
The estimated future cost to complete this contract is $3,240,000.
(a) Prepare Chicago contractors 2013 journal entries using completed contract method.
(b) Show how the contract accounts will appear in the Balance Sheet of Chicago Contractors on 12/31/2013.