Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Complete problems 2.18 and 2.19 in Ch. 2 Exercises section of the textbook attached . Note that #18 shows that activity C can't be crashed at all by showing the crash time and cost to be the same as t

Complete problems 2.18 and 2.19 in Ch. 2 Exercises section of the textbook attached .

Note that #18 shows that activity C can't be crashed at all by showing the crash time and cost to be the same as the normal time and cost.

However, #19 shows that activity E can't be crashed at all by showing the crash time and cost to be "-",

I don't know why the text did this, but they mean the same thing. Maybe it was just to show two different accepted ways of indicating an activity can't be crashed.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question