Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

contractor is calculating the probable profit on a project that is underway. the calculations show contract amount is 25,000. the original estimated...

contractor is calculating the probable profit on a project that is underway. the calculations show contract amount is 25,000. the original estimated project cost is 18,700. the revised estimated project cost is 19,350. What is the difference in percentage of profit between the orginial estimated cost and the revised estimated cost?

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question