QUESTION

Create a AON Structure and determine the Critical path; This is the Work Breakdown Structure, and the times for completion: Initiation: 32 days Sept 1-October 3, 2020 Planning 15 days October 3

Create a AON Structure and determine the Critical path; 

This is the Work Breakdown Structure, 

and the times for completion:

Initiation: 32 days Sept 1-October 3, 2020 

Planning 15 days October 3-October 18th 2020 

Integration:: 92 days October 18th-January 12 2021 

Management & Control: 34 days January 12 2021-February 13th 

Closing: 31 days February 13th-March 16th

Show more
Finesttutor
Finesttutor
  • @
  • 15 orders completed
ANSWER

Tutor has posted answer for $10.00. See answer's preview

$10.00

****** find attached your ****** Kindly **** ** * * **** ******

Click here to download attached files: AON GANNT CHART.pdf
Click here to download attached files: AON Network.xlsx
Click here to download attached files: AON Network.xlsx
Click here to download attached files: AON Network.xlsx
or Buy custom answer
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question