Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.
Develop the network activity chart and identify the critical path for a project based on the following information. Redraw the activity network as a Gantt chart. What is the expected duration of the p
Develop the network activity chart and identify the critical path for a project based on the
following information. Redraw the activity network as a Gantt chart. What is the expected
duration of the project?
Activity Expected Duration Predecessors
A 5 days —
B 6 days A
C 2 days A
D 4 days A
E 6 days B, C
F 6 days D, E
G 12 days F
H 4 days G
I 6 days F
J 7 days H, I