During a team meeting, a team member asks about the measurements that will be used on the project to judge performance.
During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned him are not valid measurements. The project is BEST considered in what part of the project management process?
- A-) Initiating
- B-) Executing
- C-) Monitoring & Controlling
- D-) Closing