Answered You can buy a ready-made answer or pick a professional tutor to order an original one.
Economics of Risk and Uncertainty Applied ProblemsPlease complete the following two applied problems. Show all your calculations and explain your results. Problem 1:A generous university benefactor ha
Economics of Risk and Uncertainty Applied Problems
Please complete the following two applied problems. Show all your calculations and explain your results. Problem 1:
A generous university benefactor has agreed to donate a large amount of money for student scholarships. The money can be provided in one lump sum of $12 million in Year 0 (the current year), or in parts, in which $7 million can be provided at the end of Year 1, and another $7 million can be provided at the end of Year 2.
Describe your answer for each item below in complete sentences, whenever it is necessary. Show all of your calculations and processes for the following points:
- Assuming the opportunity interest rate is 8%, what is the present value of the second alternative mentioned above? Which of the two alternatives should be chosen and why?
- How would your decision change if the opportunity interest rate is 12%?
- Provide a description of a scenario where this kind of decision between two types of payment streams applies in the “real-world” business setting.
Problem 2:The San Diego LLC is considering a three-year project, Project A, involving an initial investment of $80 million and the following cash inflows and probabilities: Below is in chart form!
Year 0 Year 1 Year 2 Year 3
Probability / Cash Flow Probability / Cash Flow Probabilty / Cash Flow
0.2 50 0.1 60 0.3 70
0.3 40 0.2 50 0.4 60
0.4 30 0.3 40 0.1 50
0.1 20 0.4 30 0.2 40
Initial Investment $80 mil.
Doscount Rate 8%
Describe your answer for each question in complete sentences, whenever it is necessary. Show all of your calculations and processes for the following points:
- Describe and calculate Project A’s expected net present value (ENPV) and standard deviation (SD), assuming the discount rate (or risk-free interest rate) to be 8%. What is the decision rule in terms of ENPV? What will be San Diego LLC’s decision regarding this project? Describe your answer.
- The company is also considering another three-year project, Project B, which has an ENPV of $32 million and standard deviation of $10.5 million. Project A and B are mutually exclusive. Which of the two projects would you prefer if you do not consider the risk factor? Explain.
- Describe the coefficient of variation (CV) and the standard deviation (SD) in connection with risk attitudes and decision making. If you now also consider your risk-aversion attitude, as the CEO of the San Diego LLC will you make a different decision between Project A and Project B? Why or why not?
Carefully review the Grading Rubric https://ashford.waypointoutcomes.com/assessment/3727/preview for the criteria that will be used to evaluate your assignment.
- @
- 5213 orders completed
- ANSWER
-
Tutor has posted answer for $40.00. See answer's preview
******