Expected annual direct labor hours 40,000 Expected annual direct labor cost $625,000.00 Expected machine hours . 20,000 Expected material cost for...
150
What I have done so far on question a.
$2,425,000.00(Total Overhead) /40,000(DL hrs)=$60.23
$2,425,000.00/20,000 (Machine hrs)=$121.25
$2,425,000.00/$800,000.00(Material cost)=$3.03
$2,425,000.00/$625,000.00(Labor cost)=$3.88
Not exactly sure if question a is correct and definitely not sure how this crosswalks to question b.