for the given information kindly find the critical path and also help in calculating the project completion time Work Q / Predecessors none /

for the given information kindly find the critical path and also help in calculating the project completion time 

Work Q / Predecessors none / Duration 1 day

Work R / Predecessors Q / Duration 4 days

Work S / Predecessors Q / Duration 2 days

Work T / Predecessors Q / Duration 2 days

Work U / Predecessors T / Duration 3 days

Work V / Predecessors T / Duration 3 days

Work W / Predecessors U / Duration 2 days

Work X / Predecessors V,W / Duration 1 day

Work Y / Predecessors S,X / Duration 3 days

Work Z / Predecessors R / Duration 2 days