Answered You can hire a professional tutor to get the answer.
Heineken Co. began a construction project in 2019 at a total contract price of $150 million. The project is scheduled for completion by 2021.
Heineken
Co. began a construction project in 2019 at a total contract price of
$150 million.
The
project is scheduled for completion by 2021. During 2019, Heineken
incurred $36 million of
costs and estimates an additional $84 million of costs to complete the project. In 2020, Heineken
incurred costs of $58.5 million and estimated an additional $40.5 million in costs to complete the
project. Heineken
recognizes revenue on
all contracts
over time, as the project is being completed
by using the cost to cost approach.
_____ 13.In their 2020 income statement
, Heineken
would:
A)
Recognized $15 million gross profit on the project.
B)
Recognized $13.5 million gross profit on the project.
C)
Recognized $6 million gross profit on the project.
D)
Recognized $1.5 million gross profit on the project.