Critical path.
(American Society for Quality, 2008).
Critical path = path A-B-D-E-G-H-L-M-N-O-Q-R
Project Time
Project time equals adding the durations for the activities in the critical path.
= 4 + 6 + 2 + 2 + 6 + 12 + 4 + 4 + 2 + 6 + 1
= 49 days.
If the project begins on July 6, 2009, Activity A would take 4 days to end on July 9 2009, activity B starts on 10 July up to July 17 2009, activity D starts on July20 2009 and ends on July 21 2009. Activity E would start on July 22 2009 and end on July 23 2009 while on July 24 2009, activity G runs up to July 31 2009. This would pave the way for activity H that would begin on August 3 2009 and run up to August 18 2009.
Activity L starts on August 19 2009 and take 4 days up to August 24 2009. Activity M starts on August 25 2009 up to August 28 2009 and activity N goes on till September 1. Activity O starts on September 2 2009, till September 9 2009 and activity Q ends on September 10 2009. Activity R ends on September 11 2009.
A 1 day delay on activity J would not affect the duration of the whole project since activity L can wait for 12 days for activity H to end. Completing activity O one day before schedule would reduce project days by one day. Activity C can not affect the duration for he whole project.
A network diagram is a logical approach of representing several activities which indicate the flow or sequence of a certain project. It is used to indicate the path of the project and all its activities and the starting and finishing time for every activity.