Answered You can hire a professional tutor to get the answer.

QUESTION

Hello, I am looking for someone to write an article on The major factors of business expansion. It needs to be at least 2500 words.

Hello, I am looking for someone to write an article on The major factors of business expansion. It needs to be at least 2500 words. Total float for the entire project is the sum of all floats of the activities.

.

Critical path.

(American Society for Quality, 2008).

Critical path = path A-B-D-E-G-H-L-M-N-O-Q-R

Project Time

Project time equals adding the durations for the activities in the critical path.

= 4 + 6 + 2 + 2 + 6 + 12 + 4 + 4 + 2 + 6 + 1

= 49 days.

If the project begins on July 6, 2009, Activity A would take 4 days to end on July 9 2009, activity B starts on 10 July up to July 17 2009, activity D starts on July20 2009 and ends on July 21 2009. Activity E would start on July 22 2009 and end on July 23 2009 while on July 24 2009, activity G runs up to July 31 2009. This would pave the way for activity H that would begin on August 3 2009 and run up to August 18 2009.

Activity L starts on August 19 2009 and take 4 days up to August 24 2009. Activity M starts on August 25 2009 up to August 28 2009 and activity N goes on till September 1. Activity O starts on September 2 2009, till September 9 2009 and activity Q ends on September 10 2009. Activity R ends on September 11 2009.

A 1 day delay on activity J would not affect the duration of the whole project since activity L can wait for 12 days for activity H to end. Completing activity O one day before schedule would reduce project days by one day. Activity C can not affect the duration for he whole project.

A network diagram is a logical approach of representing several activities which indicate the flow or sequence of a certain project. It is used to indicate the path of the project and all its activities and the starting and finishing time for every activity.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question