Answered You can hire a professional tutor to get the answer.
Homework: Crashing and Earned Value Problems 1. Using the network below and the additional information provided, find: a) The crash cost per day per
1. Using the network below (pls see the attached document)and the additional information provided, find: a) The crash cost per day per activity [5 points]b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? [5 points]c) Find the new budget (or cost of the project) [5 points]2. Using the network below (pls see the attached document) and the additional information provided, find: a) The crash cost per day per activity [7 points]b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? [6 points]