Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

I'm working with EVA forcasting and I need help with figuring out the AC, PV, EV, SV, SPI, and CPI values for a project. Phase 1 100% 100% $500,000

I'm working with EVA forcasting and I need help with figuring out the AC, PV, EV, SV, SPI, and CPI values for a project.

Phase 1100%100%$500,000$678,950Phase 275%60%$1,675,000$1,435,663Phase 310%5%$3,100,000$321,120Acme  Project$5,275,000$2,435,733

Phase 1

100%

100%

$500,000

$678,950

Phase 2

75%

60%

$1,675,000

$1,435,663

Phase 3

10%

5%

$3,100,000

$321,120

Acme  Project

$5,275,000

$2,435,733

Question #2What is are the EAC and ETC values IF: a)   We assume performance won't change, so we will modify the budget to accommodate using the CPI as a modifying factor.  Applying it to the remainder of the project assumes we will continue at the same rate of cost efficiency.b)  We assume our project is experiencing atypical variances that is NOT going to continue and that the project performance will likely improve. Future spending will be at the original, planned spending rate.c)   We assume we can't move the date; we will increase the budget if needed.   We think the CPI and SPI are predictive going forward.
Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question