Instructions: The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s): Activity- A. Create the EHR visionDuration (days)- 5Predecessor-

Instructions:

The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s):

  • Activity- A. Create the EHR vision
    • Duration (days)- 5
    • Predecessor- none
  • Activity- B. Identify the planning horizon
    • Duration (days)- 10
    • Predecessor- A
  • Activity- C. Obtain buy-in from affected parties
    • Duration (days)- 30
    • Predecessor- B
  • Activity- D. Develop a financing and acquisition strategy
    • Duration (days)- 10
    • Predecessor- C
  • Activity- E. Develop functional, data, and technical strategies
    • Duration (days)- 45
    • Predecessor- C
  • Activity- F. Conduct vendor selection
    • Duration (days)- 45
    • Predecessor- D, E
  • Activity- G. Plan the EHR implementation
    • Duration (days)- 15
    • Predecessor- C, E, F
  • Activity- H. Conduct benefits realization study
    • Duration (days)- 10
    • Predecessor- A-G

Use the factors listed above to:

  1. Create the PERT chart for this implementation
  2. Indicate the critical path on the PERT chart
  3. Design the GANTT chart for this implementation

Assignment Objectives:

  • Meet CAHIIM Curriculum requirement for Bachelor Degree
    1. Domain VI. Leadership
    2. Subdomain VI.I. Project Management
    3. Section 3. Apply project management techniques to ensure efficient workflow and appropriate outcomes
    4. Competencies: GANTT Charts, benchmarking, risk analysis, team structure
Show more
  • @
  • 749 orders completed
ANSWER

Tutor has posted answer for $15.00. See answer's preview

$15.00

******

Click here to download attached files: EHR Implementation.docx
or Buy custom answer
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question