Instructions: The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s): Activity- A. Create the EHR visionDuration (days)- 5Predecessor-
Instructions:
The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s):
- Activity- A. Create the EHR vision
- Duration (days)- 5
- Predecessor- none
- Activity- B. Identify the planning horizon
- Duration (days)- 10
- Predecessor- A
- Activity- C. Obtain buy-in from affected parties
- Duration (days)- 30
- Predecessor- B
- Activity- D. Develop a financing and acquisition strategy
- Duration (days)- 10
- Predecessor- C
- Activity- E. Develop functional, data, and technical strategies
- Duration (days)- 45
- Predecessor- C
- Activity- F. Conduct vendor selection
- Duration (days)- 45
- Predecessor- D, E
- Activity- G. Plan the EHR implementation
- Duration (days)- 15
- Predecessor- C, E, F
- Activity- H. Conduct benefits realization study
- Duration (days)- 10
- Predecessor- A-G
Use the factors listed above to:
- Create the PERT chart for this implementation
- Indicate the critical path on the PERT chart
- Design the GANTT chart for this implementation
Assignment Objectives:
- Meet CAHIIM Curriculum requirement for Bachelor Degree
- Domain VI. Leadership
- Subdomain VI.I. Project Management
- Section 3. Apply project management techniques to ensure efficient workflow and appropriate outcomes
- Competencies: GANTT Charts, benchmarking, risk analysis, team structure
- @
- 749 orders completed
- ANSWER
-
Tutor has posted answer for $15.00. See answer's preview
******