Answered You can hire a professional tutor to get the answer.
It takes 2 hours of direct labor to produce a carving. Bartels" standard labor cost is $12 per hour.
It takes 2 hours of direct labor to produce a carving. Bartels" standard labor cost is $12 per hour. During August, Bartels produced 10,000 carvings and used 21,040 hours of direct labor at a total cost of $250,376. What is Bartels" labor rate variance for August? Bradford Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units. What is the direct materials quantity variance and the direct materials price variance?