Job 593 was recently completed. The following data have been recorded on its job cost sheet:
Job 593 was recently completed. The following data have been recorded on its job cost sheet:
Direct materials$3,190 Direct labor-hours71labor-hoursDirect labor wage rate$ 15per labor-hourMachine-hours.175machine-hours
The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:
$6,705
$3,219
$5,249
$4,255