QUESTION

Job wr53 at nw fab, inc. required $200 of direct materials and 10 direct labor hours at $15 per hour. estimated total overhead for the year was $760,000 and estimated direct labor hours were 20,000. a

Job wr53 at nw fab, inc. required $200 of direct materials and 10 direct labor hours at $15 per hour. estimated total overhead for the year was $760,000 and estimated direct labor hours were 20,000. assuming direct labor is the allocation base, what would be recorded as the cost of job wr53?

Show more