Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.
Launch the POM software and from the main menu choose Module-gt; Materials Resource Planning 2. Program the MRP for the problem below and solve it...
1. Launch the POM software and from the main menu choose Module-> Materials Resource Planning2. Program the MRP for the problem below and solve it with the use of POM.The marketing department is estimating product A's demand to be 60 units for week 4 and 50 units for week 6. There is a scheduled receipt of 75 units for component D at the beginning of week 2. Various other MRP related information for the finished products and the components are provided below.A C D EOn hand 12 170 9 5Lead Time 2 2 1 1Lot Size LFL 150+ multiples of 40 multiples of 224. Provide the MRP tables for all the finished products and the components for the next 6 weeks.