Answered You can hire a professional tutor to get the answer.

QUESTION

Lisa is the project manager of the fkn project for her organization. she is working with sam, the cio, to discuss a discount the vendor has offered the project based on the amount of materials that is

Lisa is the project manager of the fkn project for her organization. she is working with sam, the cio, to discuss a discount the vendor has offered the project based on the amount of materials that is ordered. lisa and sam review the offer and agree that while their project may qualify for the discounted materials the savings is nominal and they would not necessarily pursue the savings. lisa documents this positive risk response in the risk register. what risk response is this

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question