Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60...

Mass Balance Company is manufacturing a new digitalscale for use by a large chemical company. The order isfor 40 units. The first scale took 60 hours of direct labor.The second unit took 48 hours to complete.a. What is the learning rate?b. What is the estimated time for the 40th unit?c. What is the estimated total time for producing all40 units?d. What is the average time per unit for producing thelast 10 units (#31–#40)?Please show all work and explain why each answer was chosen.

Learning Curves Find coefficient DataObservation 1Observation 2 Unit number12 Time6048 Given DataGiven Data a. What is the learning rate? Learning Rate =Learning Rate = Time for...