Answered You can buy a ready-made answer or pick a professional tutor to order an original one.
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows:
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows:
20X1 20X2
Costs incurred during the year $290,000 $150,000
Estimated additional cost to complete 145,000 —
Billings during the year 260,000 265,000
Cash collections during the year 240,000 285,000
Required:
- Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.
- Record the preceding transactions in MSK’s books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.
Prepare the entry to record the construction costs incurred. Hint: Use Cash, payables, materials, etc.
Prepare the entry to record the amounts billed to the customer.
Prepare the entry to record the cash receipts from the customer.
Prepare the entry to record the construction costs incurred. Hint: Use Cash, payables, materials, etc.
Prepare the entry to record the amounts billed to the customer.
Prepare the entry to record the cash receipts from the customer.
- @
- 192 orders completed
- ANSWER
-
Tutor has posted answer for $15.00. See answer's preview
***** ** studentKindly find *** file ************* ***