Not accounting for buffer, given the data below, when would task 1 be scheduled as complete.Start Task 1: 5/12 Monday Number of testers available: 1 Percentage of time tester available: 25% Task 1 es
Not accounting for buffer, given the data below, when would task 1 be scheduled as complete.
Start Task 1: 5/12 Monday Number of testers available: 1
Percentage of time tester available: 25%
Task 1 estimate: 1 person days
Vacation/Holiday: 5/17-5/18 weekend not working