Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Planned Value (PV) The scheduled cost based on the allocation cost items such resources and material during the timeline of an activity Earned Value...

1).Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a schedule cost of $523,000 and an earned value of $535,000.A software development project at day 70 exihibits an actual cost of $78,000 and a scheduled cost of $84,000. The foreman estimates a value completed of $81,000. What are the cost and schedule variances and the CSI. Estimate the time variances

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question