Answered You can buy a ready-made answer or pick a professional tutor to order an original one.
Premier Consulting's two consultants. Avery and Baker, can be scheduled to work for clients up to a maximum of 160 hours each over the next four weeks.
5. Premier Consulting's two consultants. Avery and Baker, can be scheduled to work for clients up to a maximum of 160 hours each over the next four weeks. A third consultant, Campbell, has some administrative assignments already planned and is available for clients with projects in process. The estimated hourly requirements for each of the clients over the four-week period as follows:Client HoursA 180B 75C 100D 85Hourly rates vary for the consultant-client combination and are based on several factors, including project type and the consultant's experience. The rates (dollars per hour) for each consultant-client combination are as follows:ClientConsultant A B C DAvery 100 125 115 100Baker 120 135 115 120Campbell 155 150 140 130a. Develop a network representation of the problem.b. Formulate the problem as a linear program, with the optimal solution providing the hours each consultant should be scheduled for each client to maximize the consulting firm's billings. What is the schedule and what is the total billing?c. New information shows that Avery doesn't have the experience to be scheduled for client B. If this consulting assignment is not permitted, what impact does it have on total billings? What is the revised schedule?
- @
- 57 orders completed
- ANSWER
-
Tutor has posted answer for $10.00. See answer's preview
******* ************ *** *********** ***** and Baker *** ** ********* ** **** for ******* up to * ******* ** 160 ***** each **** *** next four *****