Problem 17-16 Chuck's Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr....
Problem 17-16
Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T). Relevant data are shown on the next page. The complication is that Mr. T wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Note: No activity can be crashed more than two weeks.
CRASHING COSTS
ActivityImmediate
PredecessorNormal Time (weeks)1st Week2nd WeekK—9$410 $415 LK7125 — NK545 45 ML4300 350 JN650 — QJ,M5200 225 PQ8— — YQ785 90 ZP690 — EndY,Z
Develop a crashing schedule. (Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)
Project Length Shorten Activity Crash Cost 39 wk— 38(Click to select)ZN and LQPM and N
37(Click to select)ZN and LQPM and N
36(Click to select)ZN and LQPM and N
35(Click to select)ZN and LQPM and N
34(Click to select)ZN and LQPM and N