Problem 8. A precision engineering company consumes 50,000 units of a component per year. The ordering, receiving and handling costs are Rs.3/- per...
Problem 8.9.
A precision engineering company consumes 50,000 units of a component per year. The ordering,
receiving and handling costs are Rs.3/- per order, while the trucking cost are Rs. 12/- per order.
Further details are as follows:
Interest cost Rs. 0.06 per units per year. Deterioration and obsolescence cost Rs.0.004 per unit
per year. Storage cost Rs. 1000/- per year for 50,000 units. Calculate the economic order quantity,
Total inventory carrying cost and optimal replacement period.