Project managers should focus on: Activities that will be performed in the near term. Why? Activities that have a large cost estimate. Why?

Project managers should focus on:

  • Activities that will be performed in the near term. Why?
  • Activities that have a large cost estimate. Why?

Review this formula and address the questions:

Cost variance = Cumulative earned value – Cumulative actual cost

What does it mean when cost variance is positive? What does it mean when cost variance is negative? When evaluating a work package with a negative cost variance, what two types of activities should you focus on? Why?

Project managers should focus on:Activities that will be performed in the near term. Why?Project managers should focus on activities that will be performed in the near term. This is duesto a...