Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

Project Model Part 2/MS Project for kim woods only

Case Study: Project Model Part 2 Instructions

The following will be submitted in one document.

1.                           Open a new project in Microsoft Project. Save the file in this format: LastName_Project_Name

2.                           Have the entire project as the first task you input (that is, input the name of your project on the first line). Provide some overarching information about your project. In the Notes file, describe the project and list the key deliverables. Include any other information that may be helpful to your project.

3.                           Establish a project start date. In the Notes section, explain why you selected this date.

4.                           Create a work breakdown structure (WBS) by decomposing the scope for your project into deliverables and enter these as “tasks” in your project file. You must have at least 5 deliverables.

5.                           Decompose the deliverables further into work packages (tasks) and enter them under your deliverables. It is helpful to keep your deliverables as nouns, and to use verbs for each task. Include enough detail to have 20–25 unique tasks.

6.                           Use the “Indent Task” button to create a hierarchy that delineates deliverables and tasks.

7.                           Code the project following the 1.1, 1.1.1, 1.2 format.

8.                           Establish the project schedule by estimating time durations for all of your individual tasks. Enter the duration (in days) for each task.

9.                           Using a task’s Notes feature, justify the time estimates for at least 5 tasks. For example, you might make the following note: “This will take 3 days to allow the paint to dry before applying the trim.”

10.                     Enter at least 3 milestones for your project. Milestones typically use passive verbs (i.e. Phase 1 completed) and do not have any duration assigned to them (0 days).

11.                     Link all of your individual tasks and milestones. You can use the “link” button (appears as a chain link) after selecting the 2 tasks to be linked. Note that there are numerous ways to link tasks. Vary your linkages by including at least 2 relationships that are not Microsoft Project’s default (Finish-to-Start) relationships.

12.                     Not all tasks start immediately after a task ends (they “lag”) or wait until a task is completely finished before starting (they “lead”). Therefore, have at least 1 task include lead time or lag time. In the Notes section for this task, indicate why there would be a lead/lag for that particular task.

13.                     Next, begin to assign workers and estimate your resource costs. Enter at least 6 human resources on the Resource Sheet.

14.                     Add comments to at least half of your resources to provide information about those resources. Note things such as why they were selected, potential scheduling issues, a potential back-up, or other information that a project manager might find helpful.

15.                     In order to determine the budget for your project, you must input your labor costs. After your resources are entered, include wage rates for each individual resource.

16.                     For every task, assign the appropriate resource(s). Do not assign resources to summary tasks (your deliverables) or milestones (event markers).

17.                     If Microsoft Project displays a red human resource icon, the associated resource is over-allocated. Determine how best to address the problem and make the needed changes. If a resource can be over-allocated, justify the “why” in the task’s Notes.

18.                     When tasks, costs, and resources are entered correctly and you have double-checked for accuracy, set the project baseline. This sets the budget and schedule for the project.

19.                     Next, display the project as a network diagram to show the critical path in your project.

20.                     Submit the document in Blackbard.  

I will send you part 1

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question