Answered You can hire a professional tutor to get the answer.

QUESTION

QUESTION 6 1.The total direct materials variance is best explained by: the variance cannot be explained unless the budget is flexed to actual...

QUESTION 6

the variance cannot be explained unless the budget is flexed to actual production.

better use of materials by the production manager.

a change in price of the raw materials.

the production manager failing to control the material usage.

QUESTION 7

variance where the actual performance falls short of the budget target.

variance where labour efficiencies have occurred.

combination of variances.

variance where actual performance exceeds the budget target.

QUESTION 8

rewarding exceptional effort.

delegating responsibility, leaving management free for other things.

concentrating most of management's efforts on those who do not achieve the budget.

motivating staff to boost the reputation of the business.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question