Question:Scenario 12.2 - Hamsterdam Marlo Stanfield's operation also uses large quantities of prepaid cell phones, on average 1500 per week with a...
Question:Scenario 12.2 - Hamsterdam
Marlo Stanfield's operation also uses large quantities of prepaid cell phones, on average 1500 per week with a standard deviation of 145. The lead time for their own brand of prepaid cell phones is three weeks and they have a lot size of 350 phones. To ensure they never run out, they keep a safety stock of 500 phones with Proposition Joe.
What safety stock should be held to put the fill rate at 0.99?
0 phones
100 phones
251 phones
145 phones