Answered You can buy a ready-made answer or pick a professional tutor to order an original one.
SAINT GB334 FINAL EXAM
Question 1. 1.In a PERT network, the earliest (activity) start time is the: (Points : 2)
earliest time that an activity can be finished without delaying the entire project
latest time that an activity can be started without delaying the entire project
earliest time that an activity can start without violation of precedence requirements
latest time that an activity can be finished without delaying the entire project
none of the above
Question 2. 2.Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, what is the PERT variance for this activity? (Points : 2)
2.33
5.44
8.00
64.00
None of the above
Question 3. 3.The expected time in PERT is: (Points : 2)
a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time
the modal time of a beta distribution
a simple average of the most optimistic, most likely, and most pessimistic times
the square root of the sum of the variances of the activities on the critical path
none of the above
Question 4. 4.According to the table below, there are five activities in a PERT project.
Click here to view a Word version of the table.
Using the data in the table, if the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance respectively would be used?
(Points : 2)
20; 4.222
30; 5.222
20; 5.222
30; 4.222
22.667; 1.111
Question 5. 5.The following table represents a project with four activities. All times are in weeks.
Click here to view a Word version of the table.
Using the data in the table, what is the critical path?
(Points : 2)
A-B
A-C
B-D
A-B-C-D
None of the above
Question 6. 6.Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (assume 8-hour days). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of waiting in line is assumed to be $8 per hour.
What is the average number of people waiting to open accounts? (Points : 2)
3.27
4.16
5.27
5.83
Question 7. 7.A suburban specialty restaurant has developed a single drive-thru window. Customers order, pay, and pick up their food at the same window. Arrivals follow a Poisson distribution while service times follow an exponential distribution. If the average number of arrivals is 6 per hour and the service rate is 2 every 15 minutes, how much time will elapse (in hours) from the time a customer enters the line until he/she leaves the restaurant? (Points : 2)
0.50
0.25
0.75
2.25
3.00
Question 8. 8.A widely used mathematical programming technique designed to help managers and decision making relative to resource allocation is called __________. (Points : 2)
linear programming
computer programming
constraint programming
goal programming
None of the above
Question 9. 9.Consider the following linear programming problem:
Maximize 12X + 10Y
Subject to:
4X + 3Y ? 480
2X + 3Y ? 360
all variables ? 0
The maximum possible value for the objective function is __________. (Points:2)
360
480
1,520
1,560
none of the above
Question 10. 10.If items being transported must go through an intermediate point before reaching a final destination, then this situation is known as a(n) __________. (Points : 2)
transshipment problem
assignment problem
transportation problem
intermediate point problem
None of the above
Question 11. 11.Which of the following is not a popular definition of quality? (Points : 2)
Quality is the totality of features and characteristics of a product or service that bears on its ability to satisfy stated or implied needs.
Quality is defined as a competitively priced product that surpasses customer needs.
Quality is the degree to which a product conforms to design or specification.
Quality is fitness for use.
Even though quality cannot be defined, you know what it is.
Question 12. 12.Variations that usually occur in a process are called __________. (Points : 2)
process variations
natural variations
control variations
assignable variations
none of the above
Question 13. 13.A feasible solution to a linear programming problem: (Points : 2)
must be a corner point of the feasible region.
must satisfy all of the problem’s constraints simultaneously.
need not satisfy all of the constraints, only the non-negativity constraints.
must give the maximum possible profit.
must give the minimum possible cost.
Question 14. 14.Click here to view a Word version of the table.
To guarantee that cans of soup are properly filled, some cans are sampled and the amounts measured. The overall average for the samples is 12 ounces. Each sample contains 10 cans. The average range is 0.4 ounces.
Using the data in the table above, what is the lower control chart limit for the sample averages? (Points : 2)
12.1232
11.8768
13.2
12.308
None of the above
Question 15. 15.Which of the following control charts is/are for attributes? (Points : 2)
p-chart
x-bar chart
R-chart
A and B
A, B, and C
Question 16. 16.A certain firm has four different operations that must be assigned to four locations. The profit (in thousands of dollars) associated with each operation at each location is presented below. The firm’s vice president would like to assign the various operations so that the total profit is maximized. Find the appropriate assignments.
Click here to view an Excel version of the table.
Using the data in the table, what is the optimal location for Operation Z? (Points : 2)
1
2
3
4
Question 17. 17.Given the table below, the final table for an assignment problem, who should be assigned to Job 2?
Click here to view an Excel version of the table.
(Points : 2)
Worker A
Worker C
Either worker A or worker C
Neither worker A nor worker C
Worker D
Question 18. 18.A company believes a process monitored by an x-bar chart to be in control. When the most recent control point exceeded the UCL value by 20%, the company should: (Points : 2)
believe that a random bad luck chance occurred and proceed.
suspect that an assignable cause of variation now exists and can be found.
ignore the control point completely, as it is simply an outlier.
wait for the next four samples to be taken to see if a trend develops.
none of the above.
Question 19. 19.Click here to view a Word version of the table.
Bags of chocolate candy are sampled to ensure proper weight. The overall average for the samples is 36 ounces. Each sample contains twelve bags. The average range is 1.3 ounces.
Using the data in the table above, what is the lower control chart limit for the sample averages? (Points : 2)
36.3730
36.4849
35.6270
35.5150
Question 20. 20.Consider the following linear programming model:
Minimize 2X1 + 3X2
Subject to:
X1 + X2 ? 4
X1 ? 2
X1, X2 ? 0
This linear programming model has: (Points : 2)
a unique optimal solution.
an unbounded solution.
an infeasible solution.
an alternate optimal solution.
redundant constraints.
Question 21. 21.When using the shortest-route technique, the second step is to: (Points : 2)
find the next-nearest node to the origin and put the distance in a box by the node.
trace the path from the warehouse to the plant.
determine the average distance traveled from source to end.
find the nearest node to the origin and put a distance box by the node.
None of the above is correct.
Question 22. 22.The shortest-route technique would best be used to: (Points : 2)
assign workers to jobs in the cheapest manner.
determine the number of units to ship from each source to each destination.
determine the amount of LAN network wiring within a building.
minimize the amount of traffic flow on a busy highway.
determine the path for a truck making frequent but repeatable drops.
Question 23. 23.The p-chart is useful when we: (Points : 2)
take a number of measurements and compute the average.
take a number of measurements and compute the ranges.
find the fraction of the production lot defective.
find the number of defective items in a production lot.
None of the above is correct.
Question 24. 24. A finite population model differs from an infinite population model because there is a random relationship between the length of the queue and the arrival rate. (Points : 2)
True
False
Question 25. 25.The wait time for a single-channel system is more than twice that for a two-channel system using two servers working at the same rate as the single server. (Points : 2)
True
False
Question 26. 26.The maximal-flow technique finds the maximum flow of any quantity or substance through a network. (Points : 2)
True
False
Question 27. 27.Two characteristics of arrivals are the line length and queue discipline. (Points : 2)
True
False
Question 28. 28.The points on the network are referred to as nodes. (Points : 2)
True
False
Question 29. 29.In the maximal-flow technique, a zero (0) means no flow or a one-way arc. (Points : 2)
True
False
Question 30. 30.Infeasibility in a linear programming problem occurs when: (Points : 2)
there is an infinite solution.
a constraint is redundant.
more than one solution is optimal.
the feasible region is unbounded.
there is no solution that satisfies all the constraints given.
Question 31. 31. A certain firm has four different operations that must be assigned to four locations. The profit (in thousands of dollars) associated with each operation at each location is presented below. The firm’s vice president would like to assign the various operations so that the total profit is maximized. Find the appropriate assignments.
Click here to view an Excel version of the table.
Using the data in the table, what is the optimal location for Operation W? (Points : 2)
1
2
3
4
Question 32. 32.In a single-channel, single-phase system, reducing the service time only reduces the total amount of time spent in the system, not the time spent in the queue. (Points : 2)
True
False
Question 33. 33.A company can decide how many additional labor hours to acquire for a given week. Subcontractor workers will only work a maximum of 20 hours a week. The company must produce at least 200 units of product A, 300 units of product B, and 400 units of product C. In 1 hour of work, worker 1 can produce 15 units of product A, 10 units of product B, and 30 units of product C. Worker 2 can produce 5 units of product A, 20 units of product B, and 35 units of product C. Worker 3 can produce 20 units of product A, 15 units of product B, and 25 units of product C. Worker 1 demands a salary of $50/hr, worker 2 demands a salary of $40/hr, and worker 3 demands a salary of $45/hr. The company must choose how many hours they should contract with each worker to meet their production requirements and minimize labor cost.
Assuming this is a linear programming problem, which of the following is the optimal solution? (Points : 2)
X1 = 7.69; X2 = 0; X3 = 9.23
X1 = 0; X2 = 7.69; X3 = 9.23
X1 = 0; X2 = 9.23; X3 = 7.69
X1 = 9.23; X2 = 7.69; X3 = 0
Question 34. 34.A company must assign mechanics to each of four jobs.
Click here to view an Excel version of the table.
The time involved varies according to individual abilities. The table shows how many minutes it takes each mechanic to perform each job. If the optimal assignments are made, how many total minutes would be required for completing the jobs? (Points : 2)
0
4
17
16
None of the above
Question 35. 35.The customer who arrives at a bank, sees a long line, and leaves to return another time is __________. (Points : 2)
balking
cropping
reneging
blithering
none of the above.
uestion 36. 36.Two models of a product — Regular (X) and Deluxe (Y) — are produced by a company. A linear programming model is used to determine the production schedule. The formulation is as follows:
Maximize profit = 50X + 60Y
Subject to:
8X + 10Y ? 800 (labor hours)
X + Y ? 120 (total units demanded)
4X = 5Y ? 500 (raw materials)
all variables ? 0
The optimal solution is X = 100, Y = 0.
How many units of the regular model would be produced based on this solution? (Points : 2)
0
100
50
120
None of the above
Question 37. 37.In PERT, we assume that: (Points : 2)
the times to complete individual activities are known with certainty.
all activities are carried out by staff from our own organization.
the total cost of a project is independent of the time to complete the project.
the total time to complete all activities on the critical path is described by a normal distribution.
none of the above.
Question 38. 38.The difference between the left-hand side and right-hand side of a greater-than-or-equal-to constraint is referred to as __________. (Points : 2)
surplus
constraint
slack
shadow price
none of the above
Question 39. 39.A suburban specialty restaurant has developed a single drive-thru window. Customers order, pay, and pick up their food at the same window. Arrivals follow a Poisson distribution while service times follow an exponential distribution. If the average number of arrivals is 6 per hour and the service rate is 2 every 15 minutes, what proportion of the time is the server busy? (Points : 2)
0.25
0.50
0.75
2.25
3.00
Question 40. 40.Which of the following is not an assumption of LP? (Points : 2)
Simultaneity
Certainty
Proportionality
Divisibility
Additivity
Question 41. 41.Practically speaking, multiple optimal solutions __________. (Points : 2)
are infeasible
are unbounded
are degenerate
are unbalanced
provide management with greater flexibility in selecting and using resources
Question 42. 42.Cars arrive at a local JLUBE franchise at the rate of 1 every 12 minutes. Service times are exponentially distributed with an average of 15 minutes. Jack Burns, the JLUBE owner, has decided to open a second work bay, i.e., make the shop into a two-channel system. Under this new scheme, the total time an average customer spends in the system will be (Points : 2)
37 minutes.
2.1 minutes.
9.6 minutes.
33.3 minutes.
24.6 minutes.
Question 43. 43.An automatic car wash is an example of a constant service time model. (Points : 2)
True
False
Question 44. 44.Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, on average, how much time will elapse from the time a customer enters the line until he/she leaves the cafeteria? (Points : 2)
0.67 minute
0.50 minute
0.75 minute
0.33 minute
1.33 minutes
Question 45. 45.A certain firm has four different operations that must be assigned to four locations. The profit (in thousands of dollars) associated with each operation at each location is presented below. The firm’s vice president would like to assign the various operations so that the total profit is maximized. Find the appropriate assignments.
Click here to view an Excel version of the table.
Using the data in the table, what is the optimal location for Operation X? (Points : 2)
1
2
3
4
Question 46. 46.Which of the following is not a property of all linear programming problems? (Points : 2)
The presence of restrictions
Optimization of some objective
A computer program
Alternate courses of action to choose from
Usage of only linear equations and inequalities
Question 47. 47.Typical resources of an organization include __________. (Points : 2)
machinery usage
labor volume
warehouse space utilization
raw material usage
all of the above
Question 48. 48.Assume that we are using a waiting line model to analyze the number of service technicians required to maintain machines in a factory. Our goal should be to: (Points : 2)
maximize productivity of the technicians.
minimize the number of machines needing repair.
minimize the downtime for individual machines.
minimize the percent of idle time of the technicians.
minimize the total cost (cost of maintenance plus cost of downtime).
Question 49. 49.The shortest-route technique might be logically used for: (Points : 2)
finding the longest time to travel between two points.
finding the shortest travel distance between two points.
finding the most scenic route to allow travel to several places during a trip on spring break.
connecting all the points of a network together while minimizing the distance between them.
none of the above.
Question 50. 50.The c-chart is useful when we: (Points : 2)
take a number of measurements and compute the average.
take a number of measurements and compute the ranges.
find the fraction of the production lot defective.
find the number of defective items in a production lot.
None of the above is correct
- @
- 177 orders completed
- ANSWER
-
Tutor has posted answer for $30.00. See answer's preview
******** * 1In * **** network *** ******** ********** ***** **** ** **** ******* * ***
******** **** **** ** ******** *** ** ******** ******* ******** the ****** ********
****** time **** ** activity can ** ******* without ******** *** ****** ********
earliest time that ** activity can ***** without violation ** ********** *************
****** time that ** ******** *** ** ******** ******* ******** *** ****** ********
**** ** *** ******
Question * 2Given ** ************** ********** **** likely *** *********** **** ********* of * ** and ** **** respectively **** ** *** **** ******** *** **** activity? (Points : 2)
****
****
****
6400
**** ** *** above
******** * **** expected time ** **** is: ******* * ***
* weighted ******* ** *** **** ********** **** most *********** time *** **** times *** **** ****** *****
*** modal time ** a beta *************
a ****** ******* ** *** **** ********** **** ****** and **** *********** ******
the ****** **** ** *** *** ** *** ********* ** the ********** ** *** ******** path
**** ** *** above
******** * 4According to *** ***** ***** there *** **** ********** ** * PERT ********
***** **** ** **** * **** ******* of *** ******
Using the **** in *** ***** ** *** ****** distribution were **** ** **** *** *********** ** ********* this project in 24 ***** ** ***** what **** *** ******** respectively would ** used?
(Points * 2)
20; 4222
*** *****
*** 5222
*** *****
****** *****
******** 5 **** following ***** ********** a project **** four ********** *** ***** *** in ******
***** **** to **** * **** ******* ** the ******
***** the **** ** the table **** is *** ******** ******
******* * ***
****
A-C
****
A-B-C-D
None ** *** ******
******** * ***** Boston *** a branch ** Bryant ******* *** ****** ** ******* ** the ********* of the ******* **** **** ******** and ******** students open ******** **** **** ******** arrived ** *** ****** ** * **** ** ** *** *** (assume ****** ***** On average ** ***** *** **** ****** staff ****** ***** *** ******* ** ******* **** ******* *********** The **** ** *********** ****** *** ** *** ******* **** ****** is **** $12 *** **** *** *** cost ** ******* in **** is ******* ** ** ** *** hour
What ** *** ******* ****** ** people waiting to open accounts? (Points : ***
327
416
****
583
******** * ** ******** ********* restaurant *** ********* a ****** ********** window ********* ***** *** and **** ** ***** **** ** *** **** ****** ******** ****** * Poisson ************ ***** ******* ***** ****** ** exponential ************ If *** ******* number ** ******** ** 6 *** **** *** the ******* rate ** * ***** ** ******* *** **** time **** ****** *** hours) **** *** **** * customer enters *** line until ****** ****** *** *********** ******* : ***
****
****
****
****
****
Question * ** widely **** ************ programming ********* ******** to help ******** and ******** ****** ******** ** ******** ********** is ****** ********** ******* : 2)
linear ************
******** ************
constraint ************
goal ************
**** ** *** above
******** * ********* the ********* linear *********** *********
******** *** + ****
Subject to:
4X * ** * ****
** + ** * ****
all ********* ? ***
******* possible ***** for the objective ******** ** ********** *********** 360
****
*****
1560
****
** *** above Question
** **** items ***** *********** must ** through ** ************ ***** ****** reaching a ***** *********** then this ********* ** ***** ** **** ********** ******* * *** *************
******** assignment
problem transportation
problem ************
***** problem ****
** *** above ********
11 11Which of *** following is *** * ******* ********** ** quality? ******* * *** *******
is *** totality ** ******** and characteristics ** * product or ******* **** bears ** *** ******* ** ******* ****** or ******* needs *******
** ******* as * ************* ****** ******* that surpasses customer ****** *******
** *** ****** to ***** * ******* ******** ** design ** ************** Quality
** fitness *** **** ****
****** ******* ****** ** ******* you know **** it is ********
** ************ **** ******* ***** in * process are called __________ ******* * *** *******
*********** natural
*********** *******
*********** **********
variations ****
** the ****** ********
** *** ******** ******** ** * linear *********** problem: (Points : 2) must
** * corner ***** of the feasible ******* must
******* *** ** *** *************** *********** simultaneously ****
not satisfy *** ** the *********** only *** non-negativity ************ must
**** the ******* ******** ******* ****
**** *** ******* possible ***** ********
14 ******* **** ** **** * Word ******* ** the ****** **
guarantee **** **** ** **** *** ******** filled **** **** are ******* and the ******* measured *** ******* average *** *** ******* is 12 ounces **** ****** contains ** cans *** ******* ***** ** ** ounces *****
*** **** ** *** ***** ***** what ** *** lower ******* chart limit *** *** ****** averages? (Points * *** 121232
*******
****
******
****
** *** ****** ********
** ******* ** *** ********* ******* ****** ****** *** *********** (Points : *** ********
*****
****** ********
A
*** B A
B *** C Question
** *** certain firm has **** ********* operations that **** ** assigned ** **** locations *** ****** *** ********* ** dollars) ********** with each ********* ** each ******** is ********* ***** The firm’s **** ********* would **** ** ****** *** various ********** ** **** the total ****** ** ********* **** the *********** ************ *****
here ** view an ***** version of the ****** Using
the data ** *** table **** ** the ******* ******** *** ********* ** ******* * *** **
2
3
**
********
** ******* the ***** ***** *** ***** ***** for ** ********** problem *** should be ******** ** *** *** *****
**** ** **** ** ***** version of *** ****** *******
* 2) ******
** Worker
** ******
****** A or ****** ** Neither
****** * *** ****** ** Worker
** ********
** 18A ******* believes * ******* monitored ** ** ***** ***** to ** in ******* **** *** **** ****** ******* ***** ******** *** *** value by *** *** ******* ******* (Points * *** believe
**** * ****** *** **** ****** ******** and proceed *******
that an ********** ***** of ********* now exists and *** be found ignore
the control point ********** ** it ** ****** ** outlier ****
*** *** **** **** ******* ** ** taken ** *** ** a ***** develops none
** *** ****** Question
** ******* **** ** **** * **** version ** the ****** ****
of chocolate candy *** ******* ** ensure ****** weight *** ******* average *** *** samples ** ** ****** **** ****** contains ****** **** The ******* ***** ** 13 ******* *****
*** **** in *** table ***** **** ** *** ***** control ***** ***** for *** ****** ********* ******* * *** *******
*******
*******
355150
Question
20 20Consider the ********* linear *********** model: ********
*** + 3X2 *******
**** **
* X2 * 4 **
? ** **
X2 * **** linear
programming ***** has: ******* : 2) a unique
******* ********* ** *********
solution ** **********
********* ** *********
******* ********* redundant constraints
******** **
****** using *** ************** ********* *** second **** is to: ******* : *** **** the
************ **** ** *** ****** *** put *** ******** ** * *** ** the ***** ***** the
**** from *** warehouse ** *** ****** determine ***
******* distance ******** **** ****** ** **** **** ***
nearest **** ** *** ****** *** *** * ******** box ** the ***** **** **
*** above ** correct ******** 22
***** shortest-route ********* ***** **** ** **** to: (Points * 2) assign *******
** **** ** the ******** ******* ********* the
****** ** ***** ** **** **** **** ****** ** **** ************ ********* ***
****** ** *** ******* ****** ****** * building ******** the
****** of ******* flow on * **** highway determine the
**** *** * ***** ****** ******** but repeatable ****** ******** 23
***** ******* ** ****** when *** (Points : *** **** a
number ** ************ and ******* *** ******** **** *
****** of ************ *** ******* *** ranges find ***
fraction ** the ********** *** ********** **** ***
number of ********* ***** ** * ********** **** None **
*** ***** ** ******** ******** **
** * finite population ***** ******* **** ** infinite ********** model ******* ***** is * ****** relationship between *** ****** of *** ***** and *** ******* rate ******* * *** ***** ******
********
**
***** **** **** *** * ************** ****** is **** **** twice **** for a two-channel ****** ***** *** ******* ******* ** the same **** ** *** ****** server ******* * *** ***** ******
********
**
***** maximal-flow ********* ***** *** ******* **** ** *** ******** ** ********* through * ******* ******* * *** ***** False
********
**
27Two characteristics of ******** are *** **** length *** queue discipline ******* * *** True ******
Question
**
***** points ** *** ******* *** ******** ** ** ***** ******* * *** ***** False
********
29
**** *** maximal-flow ********* a **** (0) ***** ** **** ** * one-way *** ******* : *** ***** ******
********
**
*************** in a ****** *********** ******* ****** when: (Points : *** ***** **
** ******** ********* * constraint
** redundant **** ****
one ******** ** optimal the ********
****** ** ********** there is
** ******** that ********* *** *** *********** given ******** **
** * ******* **** has **** different ********** that **** ** assigned to **** ********* *** ****** (in thousands of ******** ********** **** **** ********* at each ******** ** ********* ***** *** ************ **** ********* would **** ** ****** the ******* ********** so that the ***** ****** is ********* **** *** *********** ************ ***** ****
** **** ** ***** version ** *** table ***** ***
**** ** the ***** what ** *** ******* ******** *** ********* ** ******* * *** ** **
**
**
********
**
**** * ************** ************ system ******** *** ******* time **** ******* the ***** ****** of time spent ** the system *** the **** spent ** the queue ******* : *** ***** False
Question
33
*** company can ****** *** **** ********** ***** hours ** acquire *** * ***** week ************* ******* will **** **** * ******* ** 20 ***** a **** *** ******* must ******* at ***** 200 units ** ******* * *** ***** ** ******* * *** 400 units ** product * ** * **** ** **** ****** 1 *** produce 15 ***** of ******* A 10 ***** ** product * *** ** ***** ** product C ****** 2 *** ******* 5 ***** ** ******* A ** ***** ** ******* * *** ** units ** ******* * Worker * *** ******* ** ***** ** ******* * ** ***** ** ******* B *** ** ***** of product * ****** * ******* * ****** of ****** worker 2 demands * ****** ** ****** and worker * ******* * ****** of ****** The company **** ****** *** **** hours **** ****** ******** **** each worker ** **** ***** ********** ************ *** ******** ***** cost ******** ****
** * ****** programming problem ***** ** *** ********* ** *** ******* ********* ******* * 2) ** *
769;
** = ** ** * **** X1 * **
** * 769; ** * **** ** * **
** * **** ** * **** ** * ****
X2 * 769; ** = ******** 34 34A *******
must ****** ********* ** **** ** **** ***** ***** **** ** view
an Excel ******* of *** ****** The **** involved ******
********* ** individual abilities *** ***** ***** how **** minutes ** ***** **** ******** to perform **** *** If the ******* assignments *** **** *** **** total ******* would ** ******** *** ********** *** ***** ******* : 2) ** *** *** ****
**
the
above
Question
35 35The ******** who
arrives ** * **** **** * **** **** *** ****** to return ******* **** ** ********** (Points * *** balking ********* reneging blithering none
**
the
******
uestion
** ***** ****** of
* ******* ******* Regular *** *** Deluxe *** ******* *** produced ** * ******* A ****** *********** ***** ** **** to determine the production ******** *** *********** ** as ********* Maximize ****** * *** +
**** ******* **** ** * ***
* ***
****** hours) * * * ? ***
****** ***** ********** ** = ** * ***
**** materials) *** variables ? *** *******
******** is X *
*** Y * *** **** ***** ** the ******* *****
would ** ******** ***** on **** solution? ******* * *** **** 50 **** **** ** the ******
********
37
****
****
** ****** ***** *******
: *** *** ***** to ******** ********** ********** *** *****
**** ********** *** activities are carried *** ** ***** ****
our *** ************* *** ***** **** ** * ******* ** ***********
of the **** ** ******** *** ******** *** total time ** ******** all ********** **
*** ******** **** ** ********* ** * ****** distribution none ** *** above Question ** ***** **********
******* *** left-hand ****
*** ********** side ** * ************************ ********** ** ******** ** ** __________ ******* * *** surplus constraint slack ****** ****** **** of ***
******
********
**
*** ********
specialty ********** *** *********
* ****** ********** ****** ********* ***** *** *** **** ** their food ** *** same window ******** ****** a Poisson distribution while ******* times follow ** *********** distribution ** *** ******* ****** ** arrivals ** * *** **** *** *** ******* **** ** * ***** ** minutes what ********** ** *** **** ** *** server ***** ******* : *** 025 **** **** **** **** Question ** 40Which
of
***
*********
**
***
** assumption ** *** (Points : *** Simultaneity ********** **************** ************* *********** ******** ** 41Practically
speaking
********
optimal
*********
**********
******* : 2) *** infeasible *** unbounded *** *********** *** unbalanced
******* **********
**** *******
*********** **
selecting ***
using ********** ******** 42 42Cars arrive ** * local *****
franchise ** the **** ** * ***** ** ******* ******* ***** *** ************* *********** with ** average of ** ******* **** ***** *** JLUBE owner *** decided ** **** * second work bay ** make *** **** **** * two-channel ****** ***** **** *** ****** *** ***** time ** ******* ******** spends in *** system **** ** ******* * *** ** ******** ** minutes ** ******** *** minutes
246 ********
******** **
**** *********
car ****
** **
******* of * ******** service **** model ******* : 2) ***** False ******** 44 *********** enter the waiting
****
**
*** for **** ** they ***** a ********* on * ********** ************ basis The ******* rate ******* * ******* ************ while ******* times follow an exponential ************ ** *** average ****** ** ******** is four *** ****** and the ******* ******* **** ** a ****** server ** seven *** ****** ** ******* *** **** **** **** elapse from *** **** a ******** ****** the line ***** ****** ****** the cafeteria? (Points : *** *** ******* *** ******* *** minute *** *******
133 minutes
******** 45
*** *******
**** has
**** different
********** **** **** be ******** ** four ********* The profit *** ********* ** dollars) ********** with **** ********* at **** ******** is ********* ***** The ************ vice president ***** **** ** assign *** various operations ** **** the ***** ****** ** maximized **** *** appropriate ************ ***** here ** **** ** Excel ******* of
*** ****** Using *** **** in the ***** **** is
*** optimal ******** *** ********* ** (Points * 2) ** ** ** ** ******** ** ******* **
the
following
is
***
* ******** ** all ****** *********** ********* ******* * 2) *** presence of restrictions ************ of **** **********
* ******** program *********
******* of ****** **
****** ***** *****
of **** linear ********* *** inequalities Question
** ********* ********* ** ** ************ *******
********** ******* * *** machinery ****** labor volume ********* ***** ************ ***
******** ******
all of
*** ****** Question
** ******** that
** are ***** *
******* **** ***** ** ******* *** ****** ** ******* technicians required ** ******** ******** ** a factory *** goal ****** be *** ******* * *** ******** ************ ** *** ************ ******** *** ******
of ******** needing repair minimize
the ******** *** ********** machines ******** ***
******* ** idle time ** the
************ ******** *** ***** **** ***** of *********** ****
**** ** ********** ******** ** ***** ************** ********* ***** ** *********
used **** (Points * *** ******* the ******* **** ** travel ******* ***
points ******* the ******** ****** distance between *** *******
******* *** **** scenic ***** ** ***** travel
** ******* ****** ****** a **** on spring ****** connecting *** *** ****** ** * ******* together
while minimizing *** distance ******* ***** **** of the ****** ******** 50 ***** *******
is useful when ***
******* * *** take * ****** ** measurements and ******* the
******** **** a number of ************ *** compute ***
******* **** *** ******** of *** ********** lot **********
**** *** ****** of ********* ***** ** *
********** lot **** ** *** ***** ** *******