Answered You can buy a ready-made answer or pick a professional tutor to order an original one.
Saint MBA550/ MBA550 Final Exam 2016
Question
Question 1.1.The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question. (Points : 5)
successors
predecessors
successors and predecessors
followers
Question 2.2.Project management differs from management of more traditional day-to-day activities because: (Points : 5)
it has limited time frame.
it has an unlimited budget
it is more expensive
it involves more of the workforce
Question 3.3.Which of the following could not be a linear programming problem constraint? (Points : 5)
1A + 2B ≠ 3
1A + 2B = 3
1A + 2B > 3
1A + 2B < 3
Question 4.4.The theoretical limit on the number of constraints that can be handled by a linear programming problem is _____. (Points : 5)
2
3
4
unlimited
Question 5.5.Which of the list of items below is not a component of a linear programming problem? (Points : 5)
Constraints
Objective function
Decision variables
Nonlinear residual
Question 6.6.For most graphs, the constraint equations which intersect to form a solution point must be solved simultaneously: (Points : 5)
because the solution coordinates from the graph cannot be visually read with high precision.
in order to confirm the mathematically determined coordinates.
in order to determine all of the optimal point solution.
because the slope b and the y-intercept a are not always integers.
Question 7.7.For the constraints given below, which point is in the feasible region of this minimization problem?
14x + 6y = 42
x + 3y = 6(Points : 5)
x = 2; y = 5
x = 1; y = 2
x = 2; y = 1
x = 2; y = 3
Question 8.8.Binary variables are: (Points : 5)
0 or 1 only.
any integer value.
any continuous value.
any negative integer value.
Question 9.9.In a 0-1 integer programming model, if the constraint x1 - x2 = 0, it means when project 2 is selected, project 1 ________ be selected.(Points : 5)
must always
can sometimes
can never
is already
Question 10.10.For a linear programming problem, assume that a given resource has not been fully used. We can conclude that the shadow price associated with that constraint: (Points : 5)
will have a positive value.
will have a negative value.
will have a value of zero.
could have a positive, negative or a value of zero. (no sign restrictions).
Question 11.11.Thecritical path is the ________ path through the n etwork. (Points : 5)
longest
shortest
straightest
most expensive
Question 12.12.Elements of project planning include: (Points : 5)
defining project objectives
identifying activities to crash.
calculating expected times and standard deviations
conducting a "lessons learned" session
Question 13.13.Mallory Furniture buys two products for resale: big shelves (B) and medium shelves (M). Each big shelf costs $500 and requires 100 cubic feet of storage space, and each medium shelf costs $300 and requires 90 cubic feet of storage space. The company has $75,000 to invest in shelves this week, and the warehouse has 18,000 cubic feet available for storage. Profit for each big shelf is $300 and for each medium shelf is $150. If the Mallory Furniture company decides to purchase 150 big shelves and no medium shelves, which of the two resources will be left over? (Points : 5)
Investment money only
Storage space only
Investment money and storage space
Neither investment money nor storage space
Question 14.14. A linear programming model consists of: (Points : 5)
decision variables
an objective function
constraints.
all of the above
Question 15.15.The term refers to testing how a problem solution reacts to changes in one or more of the model parameters. (Points : 5)
Priority recognition
Decision analysis
Analysis of variance
Sensitivity analysis
Question 16.16.If a maximization linear programming problem consists of all less-than-or-equal-to constraints with all positive coefficients and the objective function consists of all positive objective function coefficients, then rounding down the linear programming optimal solution values of the decision variables will ________ result in a(n) ________ solution to the integer linear programming problem. (Points : 5)
always; optimal
always; non-optimal
never; non-optimal
sometimes; optimal
Question 17.17.Decision variables: (Points : 5)
measure the objective function
measure how much or how many items to produce, purchase, hire, etc.
always exist for each constraint
measure the values of each constraint
Question 18.18.Cully Turniture buys two products for resale: big shelves (B) and medium shelves (M). Each big shelf costs $500 and requires 100 cubic feet of storage space, and each medium shelf costs $300 and requires 90 cubic feet of storage space. The company has $75,000 to invest in shelves this week, and the warehouse has 18,000 cubic feet available for storage. Profit for each big shelf is $300 and for each medium shelf is $150. What is the storage space constraint? (Points : 5)
90 B + 100 M = 18000
90 B + 100 M = 18000
100 B + 90 M = 18000
500 B + 300 M = 18000
Question 19.19.Multiple optimum solutions can occur when the objective function is _______ a constraint line. (Points : 5)
unequal to
equal to
linear to
parallel to
Question 20.20.A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is ____. (Points : 5)
7.0
7.5
8.0
8.5
- @
- 177 orders completed
- ANSWER
-
Tutor has posted answer for $22.00. See answer's preview
*********
******** 11The ********** **** **** be ********* ***** to *** ***** ** ** ******** ** ******** *** ****** *** ********* ******** ** *** ******** in ******** ******* * 5)
***********
*************
********** *** predecessors
**********
Question ********* ********** differs **** ********** ** **** *********** day-to-day ********** ******** ******* * 5)
** has ******* **** ******
it has an ********* budget
** is **** **********
** involves **** ** *** **********
Question 33Which ** *** ********* ***** not ** * linear *********** ******* *********** ******* * ***
** * 2B **** **
1A + 2B * **
** + ** > **
** * ** **** 3
******** ***** *********** ***** ** *** number ** *********** **** can ** handled ** a ****** *********** problem ** ***** ******* * ***
**
3
**
unlimited
******** ******* ** *** list ** ***** ***** ** *** * ********* of * ****** *********** ******** ******* : ***
************
Objective *********
Decision variables
********* *********
Question 66For most ****** *** ********** ********* which ********* ** form * solution ***** must ** ****** *************** (Points * ***
******* the solution *********** **** the graph ****** ** ******** **** with **** precision
** ***** ** confirm *** ************** ********** ************
in ***** ** ********* *** ** *** optimal ***** *********
******* the ***** b *** *** y-intercept * *** not ****** *********
******** 77For *** constraints ***** ***** which ***** is in *** ******** ****** of this ************ problem?
*** + ** * 42
x + 3y * ******** * ***
* = ** * = **
* = ** y = 2
* * 2; * = 1
x * ** * = **
Question 88Binary ********* **** ******* * ***
** 1 only
any ******* ******
*** continuous value
*** ******** ******* ******
******** **** a 0-1 integer programming ***** if *** ********** x1 - ** * ** ***** **** ******* * is ******** ******* * ******** be *************** : ***
**** *******
*** **********
can ******
** ********
Question ******* * ****** *********** ******* ****** **** * ***** resource has *** **** fully **** ** *** conclude **** *** shadow price ********** **** that *********** (Points * ***
**** **** a ******** ******
will have a ******** ******
**** have * value ** *****
***** **** * ******** ******** ** * ***** ** **** *** sign restrictions)
******** *************** **** ** *** ******** path ******* *** * ****** ******* * ***
********
*********
************
**** **********
Question 1212Elements of project planning include: ******* : ***
******** ******* objectives
identifying ********** to crash
*********** ******** times *** standard ***********
conducting * ************* learned" session
******** 1313Mallory ********* **** *** ******** *** resale: big ******* *** *** ****** ******* *** Each *** ***** ***** **** *** requires *** ***** **** ** storage ***** *** **** ****** shelf ***** **** *** ******** 90 ***** **** of ******* ***** *** ******* has ****** ** ****** in shelves this **** *** *** ********* has ***** ***** feet ********* *** storage ****** for **** big ***** ** $300 *** for **** medium ***** is **** ** *** ******* ********* ******* ******* ** purchase 150 big ******* *** ** ****** ******* ***** ** *** *** resources will ** **** ***** ******* * ***
********** ***** only
******* space *****
********** money and ******* ******
******* ********** ***** *** storage ******
******** **** * ****** *********** model ******** of: ******* * 5)
******** **********
** objective function
************
*** of the ******
******** ******* **** ****** ** ******* *** * ******* ******** ****** ** ******* ** *** ** **** of *** ***** ********** (Points * ***
******** recognition
Decision *********
******** of *********
*********** *********
Question ****** * maximization ****** *********** problem consists of all less-than-or-equal-to *********** **** *** positive ************ and the objective ******** ******** of *** ******** ********* ******** coefficients **** ******** **** *** ****** programming optimal solution ****** of the ******** ********* will ******** ****** ** **** ******** solution to *** ******* ****** programming ******* (Points : ***
always; optimal
******* non-optimal
****** ************
********** ********
******** ************ variables: ******* * 5)
measure *** ********* function
******* how **** ** *** many ***** ** ******* purchase **** etc
always exist *** **** ***********
******* the ****** ** **** constraint
Question ********* ********* **** *** ******** *** resale: *** shelves *** *** medium ******* (M) **** *** ***** ***** $500 *** ******** *** ***** **** ** ******* space *** each ****** ***** ***** **** *** requires ** cubic **** ** storage ***** *** ******* *** ****** ** ****** ** shelves **** **** and *** warehouse has 18000 ***** **** available *** ******* ****** for **** *** shelf is $300 and *** each medium ***** ** **** **** is *** ******* ***** *********** ******* * ***
** B * *** * * 18000
** * * *** * * ******
100 * + ** * = 18000
*** * * *** * = ******
******** ************ optimum ********* *** ***** **** *** ********* ******** ** ******* a ********** **** ******* : ***
******* ***
***** ***
****** to
parallel to
******** ***** ******** ******** has an optimistic time ******** ** * **** * **** ****** **** ******** ** * **** *** * pessimistic time ******** ** ** **** *** ******** **** (in ***** ** **** activity ** ____ ******* * ***
***
75
***
**