Answered You can hire a professional tutor to get the answer.

QUESTION

Southwestern UniversityAfter 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Martin Starr, president of Southwestern University, had reached a decision. To th

Southwestern UniversityAfter 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Martin Starr, president of Southwestern University, had reached a decision. To the delight of its students, and to the disappointment of its athletic boosters, SWU would not be relocating to a new football site, but would expand the capacity at its on-campus stadium.Adding 21,000 seats, including dozens of luxury skyboxes, would not please everyone. The influential football coach, Bo Pitterno, had long argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it.The job now was to get construction going immediately after the 2001 season ended. This would allow exactly 270 days until the 2002 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Starr in the eye. “I guarantee the team will be able to take the field on schedule next year,” he said with a sense of confidence. “I sure hope so,” replied Starr. “The contract penalty of $10,000 per day for running late is nothing compared to what Coach Pitterno will do to you if our opening game with Penn State is delayed or canceled.” Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target were missed.Back in his office, Hill again reviewed the data (see Table 1 and note that optimistic time estimates can be used as crash times). He then gathered his foremen. “Boys, if we’re not 75% sure we’ll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days--also for 240 days. I want to be early, not just on time!”TABLE 1 Southwestern University Project Time Estimates (days) Activity Description Predecessor(s) Optimistic Most Likely Pessimistic Crash Cost/day A Bonding, insurance, tax structuring -- 20 30 40 $1,500 B Foundation, concrete footings for boxes A 20 65 80 $3,500 C Upgrading skyboxes stadium seating A 50 60 100 $4,000 D Upgrading walkways, stairwells, elevators C 30 50 100 $1,900 E Interior wiring, lathes B 25 30 35 $9,500 F Inspection approvals E 0.1 0.1 0.1 0 G Plumbing D, F 25 30 35 $2,500 H Painting G 10 20 30 $2,000 I Hardware/AC/metal workings H 20 25 60 $2,000 J Tile/carpeting/windows H 8 10 12 $6,000 K Inspection J 0.1 0.1 0.1 0 L Final detail work/cleanup I, K 20 25 60 $4,500 This activity contains 3 questions. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take? To create paragraphs in your essay response, type at the beginning of the paragraph, and at the end. What is the probability of finishing in 270 days? To create paragraphs in your essay response, type at the beginning of the paragraph, and at the end. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times. To create paragraphs in your essay response, type at the beginning of the paragraph, and at the end.

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question