Standard fixed overhead rate for the Dempsey Company is $2 per direct labor hour calculated based on 26,000 hour expected capacity. Actual fixed...
Standard fixed overhead rate for the Dempsey Company is $2 per direct labor hourcalculated based on 26,000 hour expected capacity. Actual fixed overhead for themonth is $51,350. Each unit requires 2 hours of direct labor. Each unit requires 20minutes of direct labor. If 13,200 units were produced, what was the fixed overheadspending variance?
Standard fixed overhead rate for the Dempsey Company is $2 per directlabor hour calculated based on 26,000 hour expected capacity. Actual fixedoverhead for the month is $51,350. Each unit...