Subcontract cost= $50/unit Holding = $10/month Stock-out cost =$ 50/unit Hiring cost = $40worker Layoffs cost= $80/worker Initial inventory =100
Subcontract cost= $50/unit
Holding = $10/month
Stock-out cost =$ 50/unit
Hiring cost = $40worker
Layoffs cost= $80/worker
Initial inventory =100 units
Units last period =1400 units(December)
Month Demand Forecast
Jan 1200
Feb 1400
Mar 1600
Apr 1800
May 1800
June 2000
July 2000
Aug 1800
Given the data above, develop a level aggregate plan where production is 1400 units /month. Use inventory and subcontracting to develop the plan. Compute the cost of this plan.