Answered You can hire a professional tutor to get the answer.

QUESTION

Suppose a work center has a setup plus run time of 30 minutes to make 50 parts.

Suppose a work center has a setup plus run time of

30 minutes to make 50 parts. Also assume it takes

10 minutes to move a standard container of 50 parts to

the next work center and the demand rate is one part per

minute throughout the day.

a. Schedule this situation by drawing a picture of when

work center A should be producing and idle and

when movements of containers take place from A to

B, the using work center.

b. How many standard containers are needed for this

part to circulate from the picture in part a?

c. Use the formula n = DT ÷ C to calculate the number

of containers.

Please provide original answers with full working solutions, i.e not copied off chegg which I also have access to

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question