Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that...
Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing the project is 95%?Round the answer to the nearest higher integer.