Answered You can hire a professional tutor to get the answer.
T Pharmacy is building a new pharmacy in Los Angeles. Here are the activities that need to be completed to get the new pharmacy built.
T Pharmacy is building a new pharmacy in Los Angeles. Here are the activities that need to be completed to get the new pharmacy built. See attachment for photo
- Draw the project diagram.
- What is the normal project length?
- What is the project length if all activities are crashed to their minimum?
- T Pharmacy loses $3,500 in profit per week for every week the pharmacy is not completed. How many weeks will the project take if we are only willing to pay crashing costs which are less than $3,500?