(TCO C) A project to remodel an office area has the following activities.
ActivityDurationPredecessors
A3 months---
B2 months---
C3 months---
D4 monthsA, B
E3 monthsA
F2 monthsB, C
G2 monthsF
H1 monthG
I4 monthsD, E, F
J5 monthsH
- What are the critical path activities?
- What is the project's scheduled completion time?
- What is the slack or float for Activity B? Show your calculations.
- What is the slack or float for Activity C? Show your calculations.
- What is the slack or float for Activity E? Show your calculations.