Task 3 network diagram

Hello, I'm sorry, I think I uploaded the wrong table for the Task 3. But looks similar just little bit different. The task3 questions are same though.

Activity

Description

Proceeding Activity

Duration (Days)

A

Agree event outline

-

5

B

Identify suitable marketing companies

A

3

C

Agree contract with marketing companies

B

2

D

Circulate brief to marketing companies

A

6

E

Agree detailed brief for event

B

6

F

Select marketing company

C, E

1

G

Send confirmation of event to employees of Cocoa-Delight

D

2

H

Agree content of marketing event

F, G

2

I

Prepare content for marketing event

H

6

J

Prepare venue for event

G

2

K

Final briefing to staff briefing prior to launch

I, J

1

L

Launch marketing campaign

K