thank you Flapjack Corporation had 7,809 actual direct labor hours at an actual rate of $12.40 per hour.
hello, plz see my work on this one please. thank you
Flapjack Corporation had 7,809 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 970 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $12.79 per hour.
The direct labor rate variance is
$3,045.51 unfavorable
$3,045.51 favorable
$8,120.12 unfavorable
$8,120.12 favorable
I got unfavorable 3rd option. i used the direct labor rate
This one :
The following data relate to direct labor costs for the current period:
Standard costs7,500 hours at $11.20Actual costs6,100 hours at $10.00What is the direct labor rate variance?
a.$23,000 unfavorable
b.$7,320 favorable
c.$23,000 favorable
d.$15,680 favorable
Option A Un favorable when using the formula for the Standard cost.