The desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table contains information on this product's task times and precedence re

The desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table contains information on this product's task times and precedence relationships:

TASK                         TASKTIME

                              (SECONDS)                     IMMEDIATEPREDECESSOR

A                                       35                                             —

B                                      25                                            A

C                                    35                                                 A

D                                 55                                                  B

E                                   5                                                B 

F                                   15                                            C

G                                30                                                E-D

H                                5                                                  F-G

b. What is the workstation cycle time?

c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.)

Show more
Dr. Paul
Dr. Paul
  • @
  • 192 orders completed
ANSWER

Tutor has posted answer for $10.00. See answer's preview

$10.00

***** ** studentFind *** attached fileThank *** *** *** *****

Click here to download attached files: ANSWERS.xlsx
or Buy custom answer
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question