Answered You can hire a professional tutor to get the answer.

QUESTION

The following product development project is scheduled to commence next month at MultiCare.

The following product development project is scheduled to commence next month at MultiCare. The project activities, their resource requirements for team members, and precedence relationships are listed in the table below. Note that only one type of resource is used by each activity: team members. There are five team members assigned to this project. (20 points total)A. What is the critical path duration for this project if the project is scheduled without resource constraints (4 pts.)?B. Given a resource constraint of five team members and a schedule found using the minimum slack heuristic, which activity should be scheduled after activity A (4 pts)?C. What is the duration of a project found subject to resource constraints found using the minimum slack heuristic (7 pts.)?D. List the set of critical activities in the resource constrained schedule (5 pts).

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question