QUESTION

The manager of a functional department (e.

The manager of a functional department (e.g., engineering or marketing) complains that the milestone schedule report she is getting is not useful in assessing the performance of her department on projects she is responsible for. The project manager should give her

work package completion reports for her department through the OBS.

cost account reports for her department through the OBS.

deliverable reports.

(a.) and (b.) above.

all of the above