The network below represents a project being analyzed by critical path methods. Activities durations are:
The network below represents a project being analyzed by critical path methods. Activities durations are:
A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, J=6, K=10, and L=3
- what task must be on the critical path, regardless of activity durations?
- what is the duration of path A-B-E-H-J?
- what is the critical path of this network?
- what is the length of the critical path?
- what is the slack time at the activity C?
- what is the latest finish of the activity H?
- if activity F were delayed by two time units, what would happen to the project duration?